Project Schedules & Crashing

Developing schedules, activity network diagrams, and determining the
critical path are important for successful projects. This assignment
allows you to work through creating diagrams, identifying critical
paths, determine which tasks to crash, as well as identify resource
constraints.

Click here to download the Microsoft Excel template to use for this Assignment.

  1. Activity Network Diagram. Using the data provided in
    the Excel template develop an activity network diagram. Note an example
    is created for you in Excel that you can alter.
  2. Critical Path. Using the data provided in the Excel
    template, determine the critical path by doing a forward and backwards
    pass. Then identify the critical path and the longest duration.
  3. Project Crashing. You are considering the decision of
    whether or not to crash your project. After asking your operations
    manager to conduct an analysis, you have determined the “precrash” and
    “postcrash” activity durations and costs, as provided in the Excel
    template. Compute the per day costs for crashing each activity and
    determine what are the top two candidates for crashing.
  4. Resource Loading. Review the resource-loading chart
    provided in the Excel template. Suppose that you can commit a maximum of
    eight resource hours per day. What are the dates on which the project
    resources are overallocated? How could you reconfigure to correct the
    overallocation?

Expert Solution Preview

Introduction:

This assignment focuses on project management techniques such as developing activity network diagrams, identifying critical paths, and determining task crashing options along with resource constraints. Students will work with Microsoft Excel templates to complete this assignment.

1. Activity Network Diagram:

To complete the activity network diagram, students must use the data provided in the Microsoft Excel template to create a visual representation of the sequencing of project activities. An example is provided for students to alter if needed.

2. Critical Path:

Using the data provided in the Microsoft Excel template, students must determine the critical path by conducting a forward and backward pass. After identifying the critical path, they must determine the longest duration.

3. Project Crashing:

After analyzing the project, students must decide whether to crash the project or not. Using the Excel template, they must compare the “precrash” and “postcrash” activity durations and costs. They must also compute the per day costs for crashing each task and determine the top two candidates for crashing.

4. Resource Loading:

Students must review the resource-loading chart provided in the Excel template and determine the dates on which the project resources become overallocated. They must then provide solutions to reconfigure and correct the overallocation issue while committing a maximum of eight resource hours per day.

In conclusion, this assignment will help students understand project management techniques and allow them to apply their knowledge to a practical scenario.

Share This Post

Email
WhatsApp
Facebook
Twitter
LinkedIn
Pinterest
Reddit

Order a Similar Paper and get 15% Discount on your First Order

Related Questions

WU Detail and Dynamic Complexity Discussion Nursing Assignment Help

Are you overwhelmed by complexity? If so, you are not alone. Peter Senge notes that people are now able to “create far more information that anyone can absorb,” and he continues to say that the “scale of complexity is without precedent” (2006, p. 69). This “detail” complexity can make managing

Pediatric Health & Medical Worksheet Nursing Assignment Help

Provider: i. Questions for HPI When did these symptoms begin? Is the child experience exercise intolerance? Any shortness of breath/signs of respiratory distress? History of genetic conditions? ii. Questions for ROS Poor feeding? Any newborn cardiac concerns? Previous cardiac history? Any pain, weakness, coldness to the extremities? Fluid retention? Cough

Health & Medical Capital Budgeting at Cleveland Clinic Nursing Assignment Help

Respond to each of the following prompts or questions: Using the information provided in the Los Reyes Hospital case study from Module Three, what capital expenditures may the selected departments need to budget? Considering the organization you selected, what is a capital expenditure that may be needed that would result

NVCC Service Implementation and Elements of Financial Nursing Assignment Help

Instructions: Part 1 1.Read Chapter 10, Capko. -Critique either Dr. Grainger’s or Mid-South Pulmomary Specialists efforts in developing  new services. -What lessons did you learn as related to new service development?   -List three main items which you must address before implementing a new service.  Instructions: Part 2 -The physicians

Healthcare is reimbursed in a variety of ways. The Nursing Assignment Help

Healthcare is reimbursed in a variety of ways. The prospective payment method is one of those ways. This paper will be about the prospective payment method where diagnosis-related groupings (DRGs) forms the basis for payment. Research and explain the origin, purpose, and description of DRGs. Include what payment is based on.

NUR 630 FIU Impact on Healthcare Systems and Public Health Nursing Assignment Help

Autism Spectrum Disorder, Intellectual Disabilities, or Childhood-Onset Schizophrenia In recent years, there have been reports linking autism to vaccinations. After studying Module 5: Lecture Materials & Resources, address the following in a well-written discussion post: Explain the controversy regarding vaccines as a possible cause of autism spectrum disorder. Does the